Wendelspanswick wrote:Just completing the groundworks on mine at the moment, or I would be if I hadn't had a chest infection for the last 4 weeks!
Trying to do everything myself without paying for any outside contractors.
Used the Backactor(digger arm) on my tractor to level the site and dig the pads for the steel frame and the footings for the walls.
Ferried 6 tons of ballast from the local quarry in the trailer behind the tractor and used it to mix the concrete in the PTO mixer for the pads and footings.
Started to lay the hollow concrete blocks on the footings up to floor level and that is as far as I have got.
Once I am 100% I will finish the block work up to floor level and then order in my structural steel work to weld the frame up with.
My biggest hurdle will be getting 6 m3 of ready mix concrete up a steep stoney track and across the meadow to pour the floor with.
I have assurances from my pals that they will lend a hand, I will hire a 5 ton dumper I think and use it to ferry the concrete in 2 loads. That's further down the line though as I am not going to pour the floor until after the roof is on.
Just a small point, but 6m3 of concrete comes in at almost 14 tons so a bit more than 2 trips in a 5 T dumper.
Also factor in your steep, stoney bank which will result in changing angles and slop of the concrete meaning you cannot take full loads to avoid significant spillage.
Probably need to look at 4 or even 5 loads.
Should not be a problem if you hire the dumper for the day - as long as you are not driving miles each way.
Just be aware that generally concrete companies dont allow for long turn-arounds so you need to mention your expected timings - which might incur extra cost.
One way to avoid this is to be flexible as to when you get your delivery and opt for a slow period.
That said, I opted for a quiet day only to find that the trucks were coming to site with long delays between as the slow day had suddenly turned very busy due to a bridge construction project being ready to pour a day earlier than scheduled.